Augmentation of Airport Primary Substation at Bandaranayake International Airport

0
  • Airport & Aviation Services (Sri Lanka) Limited
  • October 2007 to August 2008
  • Removal of Existing 2 nos of 5MVA 33/11kV Transformers.Design, Manufacture, Supply, Installation, Testing and Commissioning of following,

    • 2 nos of 10 MVA 33kV/11 V Transformer with MR Germany Make OLTC,
    • 2nos 11kV Neutral Grounding Resistors
    • 6nos of 33kV Lightning Arrest-or
    • 11kV Cable Termination
    • Control Cable Termination