Power Sector Development Transmission Project Lot A - Erection of Deniyaya Grid Substation.

 

 

(Under Construction Expected date of Completion 31.05.2009)

Client: Siemens AO GmbH/ CEB

Date commenced : March 2008

 

Scope of Work:
Erection of;

  • 132kV Line Bays – 2 nos
  • 132kV Transformer bays – 2 nos
  • 132kV Bus Section Bay – 1 no
  • 31.5 MVA 132kV/33kV Transformers – 3 Nos
  • 33kV Indoor GIS Switchgears
  • Battery and Chargers System
  • 132kV Protection, Metering and Control Panels
  • Communication Equipment
  • Switchyard Lightning Protection System
  • Earthing and Auxiliary Transformers
  • 33 kV Gantries and related work
  • Power and Control Cabling & Termination

 

Go Back

 

News & Events
Bela International has been Awarded ISO 9001:2008 Certification


Read more...
 
Help for the poor
Read more...
 
We enjoyed together at Beruwala
Read more...
 
Dawn of New Year 2009

 

Read more...
 
Current Projects

Construction of 28km, Lynx Conductor 33kV Double Circuit Tower Line From Ambalangoda Gss Thalgaswala Gantry


 

 

Read more...
 
Read more...
 

Power Sector Development Transmission Project Lot A - Erection of Deniyaya Grid Substation.

 

Read more...